Notice of Upcoming Residential Development Construction Mobilization
Notice of Upcoming Residential Development Construction Mobilization
Starting the week of January 17, 2021, Taillieu Construction
Ltd. will be mobilizing to commence installation of infrastructure for Phase 1
of the Meadowlands residential development. This involves the
installation of the underground land drainage system, water and sewer
lines. This land is located to the west of the CP Rail line, between
Addis and Prest Avenues. Work has already begun at the boat ramp area
adjacent to the Red River and is moving westward.
For your safety and to provide adequate working space for the contractor, no
parking will be allowed on the road for the duration of construction.
During construction, recycling and garbage collection will not be affected and
one lane of traffic will be maintained.To keep your children and pets safe, please keep them away from the
construction site at all times.
If you have any questions or concerns regarding this project, please contact
Ryan Loewen of Stantec Consulting Ltd.,
at 204-228-6855 during regular business hours or by email at ryan.loewen@stantec.com. The project contractor’s
contact is shown below.
- Taillieu Construction, Lorne
Furgala, Superintendent (204-793-5658)
- Gord Frantz, 24-hour emergency
(205-793-5416)