Aug. 28, 2017 - Notice of Watermain Construction
 
Work on the West St. Paul Water Project is continuing and construction of the water reservoir and pump house is ongoing. 
 
During the week of June 4-10, 2017:
 

June 5:

  •   Begin closing in formwork for West wall infill sections pump well upper wall sections.

  •   Continue scaffolding in the north cell and begin placing metal Joists.


Cartier Regional Water Cooperative
Weekly Report for the Period June 4 to June 10, 2017
Page 2 KGS 16-0429-007

June 6:

  •   Finish closing up west wall infill sections and cast concrete (approximately 30 m3).

  •   Continue scaffolding for roof slab at N.W. corner.

    June 7:

  •   General cleanup

  •   Stripping forms.

  •   Grouting walls.

  •   Continue scaffolding.

    June 8:

  •   Cast 3 infill wall sections (north, centre and south walls).

  •   Continue scaffolding placing plywood deck and forming for concrete beam.

  •   Begin forming and reinforcing steel for 2 infill sections along the west wall.

    June 9:

  •   Continue scaffolding (plywood deck).

  •   Continue forming for concrete beam.

  •   Continue grouting concrete walls. 

  • Work is on budget, and on schedule.